July 2019
California Community Colleges Continuing Capital Outlay Projects
(In Thousands)
2019-20 | All Years | |||||
College | Project | Phases | State Cost | State Cost | Total Cost | |
San Francisco (Ocean Campus) | Utility infrastructure replacement | C | $58,082 | $63,461 | $79,326 | |
Santa Monica | Science and mathematics building addition | C,E | 37,031 | 39,615 | 78,102 | |
Laney | Learning resource replacement center | C,E | 22,812 | 24,417 | 75,686 | |
Mount San Antonio | New physical education complex | C,E | 53,993 | 57,541 | 72,238 | |
Santa Rosa | Science and mathematics replacement building | C,E | 30,882 | 33,076 | 65,589 | |
Orange Coast | Language arts and social sciences replacement building | C,E | 28,305 | 30,353 | 59,803 | |
Pasadena | Armen Sarafian building seismic replacement | C | 41,221 | 45,099 | 58,961 | |
Allan Hancock | Fine arts replacement complex | C,E | 22,873 | 24,526 | 48,318 | |
Golden West | Language arts replacement complex | C,E | 21,925 | 23,540 | 46,478 | |
West Hills Coalinga (North District Center) | New library and instructional facility | C,E | 40,275 | 42,403 | 43,285 | |
Santa Ana | Russell Hall replacement | C,E | 19,192 | 20,729 | 40,948 | |
Solano | Library replacement building | C,E | 17,396 | 20,148 | 39,739 | |
Fullerton | Business 300 and Humanities 500 Renovation | C,E | 14,056 | 15,369 | 31,117 | |
Redwoods | Arts replacement building | C | 22,010 | 24,087 | 24,087 | |
Compton | Instructional replacement building 2 | C,E | 14,891 | 16,167 | 24,995 | |
Mission | Portables replacement | C,E | 10,073 | 10,814 | 21,500 | |
Merritt | Child development replacement center | C,E | 5,692 | 6,128 | 20,013 | |
Imperial | Academic buildings 200, 300, and 800 renovation | W,C,E | 8,647 | 9,043 | 17,741 | |
San Francisco (Alemany Center) | Seismic and code renovations | C | 10,933 | 12,184 | 19,553 | |
Long Beach (Pacific Coast Campus) | Construction trades building renovation, phase 1 | C,E | 6,712 | 7,304 | 13,107 | |
Totals | $487,001 | $526,004 | $880,586 | |||
Notes: | ||||||
Community college districts issue local general obligation bonds to pay for a share of project costs. | ||||||
C = construction. E = equipment. W = working drawings. |